Cost of Poor Quality Review · October 2026

Kelsmoor Kitchens and Bathrooms Ltd

Designs, supplies and fits kitchens and bathrooms for homeowners, and refits for housing associations, across Staffordshire and Cheshire; worktops cut in its own workshop. 64 staff.

Worked example. Kelsmoor Kitchens and Bathrooms and its figures are fictional. All figures come from the worked-example spreadsheet: ALL CHECKS PASSED (with 4 notes).
The headline

Failures cost £101,958 a year; three causes make 57% of it

Cost of poor quality
£101,958
a year: £77,120 cash, £21,438 staff time already in wages, £3,400 lost orders
Share of sales
1.6%
£1.59 in every £100; 39% found by the customer
Lost customers
£18,350
a year at the share counted: kept out of the headline, resting on estimates
Fixes: first-year net
£3,765
£16,034 a year after; −£4,244 if they do half as well; £5,670 in cash alone

Verdict: Failures cost about £101,958 a year (£77,120 cash, £21,438 staff time already paid in wages, £3,400 lost profit on cancelled orders): 1.6% of sales, or £1.59 in every £100. 39% of it was found by the customer. The biggest causes: Worktop template or cut error (31%); Survey measurement error (13%); Fitting workmanship (snagging) (12%); 6 of 12 causes make 80% of the cost. Customers lost: 4 lost (1 repeat or contract, 3 one-off); 1 not known, valued at £18,350 a year at the share counted, kept apart because it rests on estimates. The 5 fixes to do should save about £18,306 a year for £12,253 in the first year (£8,600 of it cash), staff time counted at the same share both ways: a first-year net of £3,765 (-£4,244 if they do half as well; £5,670 in cash alone), and £16,034 a year after. Worth doing if they work as expected, not at half.

The few causes that matter

6 of 12 causes make 80% of the cost

Worktop template or cut error£32,106 · 31% · 31% so farSurvey measurement error£13,531 · 13% · 45% so farFitting workmanship (snagging)£12,194 · 12% · 57% so far · +£225 lost customersPlumbing leak after handover£9,543 · 9% · 66% so farSupplier sent damaged or wrong goods£8,316 · 8% · 74% so farDesign or order specification wrong£7,449 · 7% · 82% so farDamaged in our van or on site£7,270 · 7% · 89% so farMissed or late appointment£5,412 · 5% · 94% so far · +£18,125 lost customersWrong item ordered by the office£2,841 · 3% · 97% so farDelivery not as booked£1,295 · 1% · 98% so farElectrics or appliance connection fault£1,053 · 1% · 99% so farInvoice or paperwork error£950 · 1% · 100% so far

Red: the causes that together make 80% of the cost. Last in: Design or order specification wrong (to 82%); next out: Damaged in our van or on site (7%, to 89%). Grey extensions: lost customers’ value at the share counted, which isn’t in the cost. With it, missed or late appointments would rank second: one housing association that didn’t renew outweighs every credit on that cause. That is why it shouldn’t stay parked for long, even though it barely registers on cost alone. Worktop template and cut errors are almost a third of the cost: quartz worktops recut in the workshop, with the hours estimated because the workshop doesn’t book them to jobs.

Where the failures were found

61% before the customer, 39% after

TypeFoundFailuresCost a yearShare
ScrapInternal32£39,37639%
Re-delivery or call-backExternal42£11,83212%
Warranty claimExternal14£10,59610%
ReworkInternal15£10,57410%
Customer complaintExternal16£10,02610%
Supplier faultInternal16£8,3168%
Return or creditExternal8£7,4497%
Internal error caughtInternal58£3,7914%

Prevention and appraisal already cost £26,088 a year (5% prevention, 16% appraisal, 80% failure). Most of that is inspection: handover checks and survey checks that find failures rather than stop them. Four of the fixes build on those checks rather than adding new ones.

By line

Cost per £100 of each line’s sales

LineSales a yearCost a yearIn every £100Customers lost
Retail kitchens
One-off
£3,300,000£66,566£2.022
Retail bathrooms
One-off
£1,150,000£21,001£1.831
Housing refits
Repeat or contract
£1,750,000£10,180£0.581
Trade worktops
Repeat or contract
£200,000£4,211£2.110
Checked against the accounts

Credit notes, scrap and warranty all within 10%

FigureLogAccountsDifferenceStatus
Credit notes and refunds for quality reasons (credits marked credit note or refund)£6,970£7,400-6%Within 10%
Scrap and damaged stock: materials on the types chosen on Inputs£47,750£46,5003%Within 10%
Warranty met: cash on warranty rows, less credit notes (checked above); own labour usually sits in wages£6,255£6,0004%Within 10%

The bookkeeper confirmed the write-off covers workshop scrap and damaged supplier goods; rework materials are charged to the job, so they are left out of that comparison. Warranty is compared on cash the provision would meet: refunds given as credit notes are checked once, against the ledger, not twice.

The fixes

5 to do; 1 parked; 5 of 6 causes in the 80% have one

Cause and fixPlanExpected saving a yearFirst-year costFirst-year netCash only, first year
Worktop template or cut error
Digital templating at the existing template visit, after the carcasses are fitted; cut list checked against the template before cutting
Error Proofing Design · worked elsewhere · 60% less if it works, 50% chance
Do£9,188£6,860£1,180£1,152
Survey measurement error
Laser measures and one standard survey sheet, checked by the senior surveyor at the existing survey check
Standard Work Documentation · root cause confirmed · 60% less if it works, 60% chance · relies on: senior surveyor checks every survey before ordering
Do£4,176£2,100£1,554£1,246
Plumbing leak after handover
Pressure test and a 30-minute leak check, photographed, before every handover
Error Proofing Design · worked elsewhere · 70% less if it works, 50% chance · relies on: handover inspection on every job
Do£2,917£1,883£670£1,882
Fitting workmanship (snagging)
Root cause analysis of the last 30 call-backs, then a photographed checklist used at the existing handover inspection
Root Cause Analysis · best practice · 40% less if it works, 30% chance · relies on: handover inspection on every job
Do£1,134£1,080−£88£704
Supplier sent damaged or wrong goods
Photos from the existing goods-in check sent with a claim to the supplier within 48 hours
Supplier agreement · best practice · 40% less if it works, 30% chance · relies on: goods-in check of deliveries
Do£891£330£450£686
Missed or late appointment
Text every customer two days before with the fitter's name and arrival window
Other · hunch · 30% less if it works, 20% chance
Park––––

Staff time is counted at the same 50% share whether a fix saves it or spends it. The leak check adds a quarter of an hour to every plumbing handover, about 390 a year, and that per-job time is in its cost.

How confident are we?

What this rests on

The log covers 12 months from 1 Oct 2025, scaled to a year; every cost comes from the business’s own records, labour at each role’s cost an hour (18% of it estimated rather than booked). Credits are net of goods resold; lost gross profit counts only where a cancelled order is evidenced. Failures nobody wrote down aren’t here: the check against the accounts shows how far the log and the accounts agree. Lost customers are valued at 50% of the owner’s estimate (assumed), less any lost order already counted, and kept out of the headline. Each fix counts at the chance it works (60% root cause confirmed, 50% worked elsewhere, 30% best practice, 20% a hunch: assumed), staff time at 50% both for time saved and time spent (assumed), building up over 3 months. No benchmark is used: the yardstick is your own cost, year on year.

The design and specification errors (7% of the cost) have no fix yet: a Root Cause Analysis would find out whether they start at the showroom or in ordering. Re-run the review in a year: the yardstick is this year’s own figure, not anyone else’s. Not legal or accounting advice.

The months after

What the agent flagged, and what was decided

After the review, Kelsmoor chose the guided route. In the final working session the agent was set up in an AI assistant the business already uses, connected read-only to the job sheets, the sales ledger and the warranty file (its IT confirmed this before it committed). On the first Monday of each month it adds the new failures to a new year's log in a dated copy of the review, runs the checks and sends the managing director a short note. It uses the rules on Inputs: a cause is trending up if, after three months, it runs 25% above its cost at the review and at more than £2,000 a year. Nothing left Kelsmoor, and no decision changed, without one of its own people approving it. These events continue the fictional example.

DateWhat the agent foundWhat was decided
2 Nov 2026
No flag
The new year's log started: 15 October failures added from the job sheets, credit notes and warranty file. Two records had no hours, so they waited for the office instead of being guessed.Nothing needed. The office manager completed the two records.
7 Dec 2026
Flag
A trade worktop customer, a kitchen fitter, closed its account after two worktops were cut short in November: a customer lost.The managing director phoned the customer, but the account stayed closed. Digital templating, already planned, was brought forward to start in December.
4 Jan 2027
Flag
A credit typed as text on a row the office completed by hand put a CHECK on the Checks sheet. The note said so, named the check and gave no figures.The office manager re-entered it. Checks passed the same morning, and the note followed.
1 Feb 2027
Flag
Plumbing leaks after handover were trending up: four months of the new log put them at £15,300 a year, against £9,543 at the review.The managing director booked a Root Cause Analysis with the plumbing lead for 9 February. It found a batch of faulty push-fit connectors, replaced in February.
1 Mar 2027
No flag
Worktop cut errors were running at £11,800 a year against £32,106 at the review, with none since digital templating started in mid-December.Nothing needed. The managing director read the note.
5 Apr 2027
No flag
Plumbing leaks were back within the 25% rise: £10,900 a year against £9,543 at the review.Nothing needed. They will be watched for two more months before the cause is closed.

At the check-in on 30 November, after the first monthly run (about day 45), Geoff and the managing director read the first log together. No rule needed changing.

What the agent added. The method is unchanged: same spreadsheet, same checks, same costs. The agent made sure the log kept being filled every month, so the leaks were caught in February instead of at next October's re-run, and the yearly re-run will start from a full log. The figures in these events are fictional log readings, not new savings: the review's value case above is unchanged and no new £ figure is claimed for the agent.

Fictional and labelled: these events continue the worked example. The same six events are the sample rows in the Agent log of the worked-example spreadsheet. The agent is part of the guided and done-for-you routes; the self-implement kit does not include it.