Crisis Response Plan · October 2026

Cragmere Foods Ltd

Chilled soups, sauces and ready meals for foodservice wholesalers, contract caterers and retailers' own-label, cooked in Brighouse and packed and despatched from Elland. 118 staff on two sites.

Worked example. Cragmere Foods and its figures are fictional. All figures come from the worked-example spreadsheet: ALL CHECKS PASSED (with 4 notes).
The headline

A plan for the first 72 hours: eight scenarios, every legal deadline mapped, every role deputised

Scenarios complete
8 of 8
owner, deadline map, legal deadlines, approved statement, spokesperson
Legal deadlines on the map
8 of 8
food safety, RIDDOR (including dangerous occurrences), the ICO, the Environment Agency
Phone numbers checked
53 of 53
different numbers, last six months; 7 of 29 at the start (24%)
First approved statement
minute 52
in the baseline exercise, before the plan; target 30

Verdict: The plan covers 8 scenarios; all are complete (owner, deadline map, legal deadlines, approved holding statement, spokesperson). Every legal deadline that applies is on the map (8), and every one of the 13 roles has a deputy. 53 of 53 different phone numbers have been checked in the last 6 months (at the start, 7 of 29). In the baseline exercise the first approved holding statement came at minute 52 against a target of 30, and 1 of 6 injects were actioned on time. The rehearsal with the plan is on 19 Nov 2026. How the value is shown (risk avoided, not a forecast): the largest event, “Key customer goes into administration”, would cost £632,750 from the owner's own figures. With the owner's assumed likelihoods, the 8 events cost £67,959 a year on average; if the plan works as assumed it cuts that by £21,169 (£10,584 if half as well), against £4,306 a year to keep up with the build spread over 5 years. Re-measure the numbers and the quiz on 16 Apr 2027.

The scenarios

One page each, each with an owner, a spokesperson and a deadline map

ScenarioOwnerRowsLegalFirst to tellComplete
S1 Allergen or foreign-body recall
Product recall · Both sites
Technical lead
speaks: Crisis lead
51Local authority food safety team
straight away
Yes
S2 Serious injury on the production line
Serious accident · Brighouse kitchen
Health and safety lead
speaks: Crisis lead
62Emergency services (999)
straight away
Yes
S3 Fire at the Brighouse kitchen
Fire or flood · Brighouse kitchen
Operations lead
speaks: Crisis lead
71Fire and rescue service (999)
straight away
Yes
S4 Ransomware or a data breach
Data breach · Both sites
IT and data lead
speaks: Crisis lead
62Insurer: cyber policy incident line
1 hour
Yes
S5 Viral complaint or video on social media
Viral complaint · Both sites
Communications lead
speaks: Communications lead
30Crisis lead
1 hour
Yes
S6 Key customer goes into administration
Key customer failure · Both sites
Finance lead
speaks: Crisis lead
50Credit insurer: overdue account notice
24 hours
Yes
S7 Chiller or power failure at Elland
Site loss or utility failure · Elland packing and despatch
Site lead (Elland)
speaks: Customer lead
30Refrigeration maintenance contractor
straight away
Yes
S8 Effluent or ammonia spill
Pollution · Brighouse kitchen
Health and safety lead
speaks: Crisis lead
52Environment Agency incident hotline
straight away
Yes
The legal deadlines

Checked against the rules on Inputs, each sourced; not legal advice

ScenarioWho must be told, and what the law saysLatestTold by
Allergen or foreign-body recallLocal authority food safety team
Food: withdraw unsafe food immediately and immediately inform the competent authorities; recall from consumers if it has reached them. You can also tell the FSA yourself once it has reached consumers (you must if FSA-approved)
straight awayTechnical lead
Serious injury on the production lineHSE: specified injury (RIDDOR)
Notify without delay (phone 0345 300 9923 for deaths and specified injuries, or online); the report must be received within 10 days
straight awayHealth and safety lead
Serious injury on the production lineHSE: if off work more than seven days (RIDDOR)
Report within 15 days of the incident, online
15 daysHealth and safety lead
Fire at the Brighouse kitchenHSE: dangerous occurrence (RIDDOR), if work stops for more than 24 hours
Notify without delay, online; the report must be received within 10 days
straight awayHealth and safety lead
Ransomware or a data breachInformation Commissioner's Office
Report a notifiable breach without undue delay and not later than 72 hours after becoming aware of it; record every breach, reported or not
3 daysIT and data lead
Ransomware or a data breachPeople affected, if the risk to them is high
Tell them directly and without undue delay
3 daysPeople lead
Effluent or ammonia spillEnvironment Agency incident hotline
Report a pollution incident straight away; an environmental permit or consent usually requires notice without delay (check yours)
straight awayHealth and safety lead
Effluent or ammonia spillHSE: dangerous occurrence (RIDDOR), an escape that could injure someone
Notify without delay, online; the report must be received within 10 days
straight awayHealth and safety lead

The rest of the map is the business’s own rules and its policies’ and contracts’ deadlines (the insurers’, the bank’s, the co-packer’s), as the owner read them.

The crisis team

Every role with a deputy who is someone else; 2 people may approve a public statement

RoleHolds itDeputyCan approveCan speak
Crisis leadHelen MRob DYesYes
SpokespersonHelen MGareth LYesYes
Operations leadRob DSanjay PYesYes
Technical leadAisha KMarta WNoNo
Communications leadLeanne FAmy CNoYes
Customer leadGareth LNina VNoYes
People leadPriya SClaire BNoNo
Finance leadMartin OClaire BNoNo
IT and data leadOwen RTom G (IT support firm, on contract)NoNo
Health and safety leadDave NSanjay PNoNo
Site lead (Elland)Kerry JDan HNoNo
Log-keeperJosh TMarta WNoNo
Legal adviserRetained solicitor (partner)Retained solicitor (associate)NoNo

Mobile and out-of-hours numbers are in the workbook and the printed contact sheet only.

One scenario in full

S1 Allergen or foreign-body recall

Likely triggers. A customer's technical team or a consumer reports an undeclared allergen or a foreign body; QA finds a label or recipe mix-up; a supplier recalls an ingredient

The first hour. Stop despatch of the batch and quarantine stock; trace every pack from the despatch records; call the customers' technical teams; tell the local authority food safety team; start the log

Who must be toldKindByTold by, and how
Local authority food safety teamLegalstraight awayTechnical lead
Phone the duty officer, then the online report
Food Standards Agency incidents team, if the product has reached consumersOur rulestraight awayTechnical lead
Online incident report, then phone
Customers' technical teams (affected batches)Our rule2 hoursTechnical lead
Phone, then email with batch codes
All staffOur rule4 hoursPeople lead
Briefing at the shift change and text alert
Insurer: product recall policyPolicy or contract24 hoursFinance lead
24-hour incident line

Holding statement (approved by the crisis lead, 14 October 2026; 96 words):

We have found that [product], batch [code], may contain [allergen or foreign body] not shown on the label. As a precaution we have stopped supplying it and are removing it from sale. If you have an allergy to [allergen], do not eat it. If you bought it in a shop, return it there for a full refund; caterers and food service customers, please stop serving it, keep it to one side and call us on [number] to arrange collection. We are working with the local authority food safety team. We will update this statement by [time].

Staff message, sent first:

We are withdrawing [product], batch [code]. Stop packing and despatching it now and move all stock to quarantine. Don't discuss this outside work or online; refer any questions to Leanne F. Update at [time].

Spokesperson: Crisis lead. Channels: Customers' technical teams by phone, then email; notice on the website; social media replies only to direct questions.

The baseline exercise

1 of 6 injects on time, before the plan existed

MinuteInject and expected actionTargetActualResult
0A customer's technical manager rings: a consumer reports a reaction to the chicken and mushroom soup; the label shows no celery
Expected: Technical lead takes the details, quarantines the batch and calls the crisis lead
109On time
10QA finds the stock pot with celery was used on that batch; 1,900 packs are in three customers' depots
Expected: Decide to withdraw; trace every pack from despatch records
2031Late
20A regional radio newsdesk calls reception asking about a recall
Expected: Reception refers the call to the communications lead, who gives the holding line
25–Not done
30A photo of the pack is shared 400 times on social media
Expected: Holding statement posted as one reply; monitoring started
4052Late
40The local authority food safety officer asks what has been done so far
Expected: Technical lead reports the actions and the recall plan
45–Not done
50Two customers ask for a written update
Expected: Customer lead sends an approved update
5558Late
What we learnedActionStatus
Nobody knew the local authority must be told immediatelyDeadline map on every scenario page; deadlines quiz for the team
Technical lead, by 14 Oct
Done
Reception told the radio newsdesk 'no comment'Brief reception and the switchboard: one line and the communications lead's number
Communications lead, by 23 Oct
Open
The statement was drafted from scratch by four people and approved at minute 52Pre-approved holding statement for each scenario
Communications lead, by 14 Oct
Done
Two numbers on the old contact list were dead, one of them the insurer's claims lineCheck every number, deputies included, every six months
Log-keeper, by 15 Oct
Done
No one recorded decisions or timesA log-keeper with a deputy; the log form in the plan
Crisis lead, by 14 Oct
Done
The customer lead was on holiday and nobody coveredA deputy for every role
Crisis lead, by 14 Oct
Done
How the value is shown

Risk avoided: the cost of each event from the owner’s own figures; the likelihoods are the owner’s assumptions, never facts

Allergen or foreign-body recall£249,265£141,163Serious injury on the production line£22,862£17,431Fire at the Brighouse kitchen£269,536£182,802Ransomware or a data breach£59,312£26,725Viral complaint or video on social media£42,000£16,000Key customer goes into administration£632,750£540,500Chiller or power failure at Elland£23,104£14,052Effluent or ammonia spill£44,052£19,052

Without the plan With the plan (the owner's assumption)

ScenarioCost without the planWith the planReductionLikelihood (assumed)Expected cost a yearBreak-even: once in N years (half as well)
Allergen or foreign-body recall
direct costs estimated
£249,265£141,163£108,1021 in 20
own history
£12,46325 (13)
Serious injury on the production line
direct costs estimated
£22,862£17,431£5,4311 in 7
own history
£3,4291 (1)
Fire at the Brighouse kitchen
direct costs quotation
£269,536£182,802£86,7341 in 100
insurer or adviser's view
£2,69520 (10)
Ransomware or a data breach
direct costs estimated
£59,312£26,725£32,5871 in 10
insurer or adviser's view
£5,9318 (4)
Viral complaint or video on social media
direct costs quotation
£42,000£16,000£26,0001 in 7
owner's judgement
£6,3006 (3)
Key customer goes into administration
direct costs counted
£632,750£540,500£92,2501 in 20
owner's judgement
£31,63821 (11)
Chiller or power failure at Elland
direct costs counted
£23,104£14,052£9,0521 in 5
own history
£4,6212 (1)
Effluent or ammonia spill
direct costs estimated
£44,052£19,052£25,0001 in 50
owner's judgement
£8816 (3)

Each cost is lost gross profit (£18,104 a working day, counted from the accounts, times the days and share of output lost, less any business interruption cover), customers’ gross profit lost in the rest of the year after the days disrupted (from the sales ledger, less the insured share inside the 12-month indemnity period) and direct costs net of what the insurer would pay. The plan’s effect on days and customers, and how much less the insurer would pay without it (S6 and S8), are the owner’s assumptions. The break-even column needs no likelihood: the yearly cost (upkeep plus the build spread over five years) is covered if the plan saves its assumed amount on that event once in that many years. With the owner’s assumed likelihoods (not a forecast), the events cost £67,959 a year across 8 scenarios on average; if the plan works as assumed it cuts that by £21,169 a year; £10,584 if half as well. Cost in full: £6,288 to build; £3,048 a year to keep up (48 hours); £4,306 a year with the build spread over 5 years. The largest event, the key customer’s administration, the plan can barely touch: it protects only the credit insurance claim, and that only on the owner’s assumption about a missed overdue notice.

The readiness measures

Taken at the baseline, again at the rehearsal on 19 November 2026, and at the re-measure

MeasureAt the startNowAfter the rehearsalRe-measure
Different phone numbers checked in six months7 of 29 (24%)53 of 53 (100%)–16 Apr 2027
First approved holding statement in the exerciseminute 52–target minute 30–
Injects actioned on time1 of 6–to be logged–
Deadlines quiz: answers right41%–the same people, same questions16 Apr 2027

One exercise and nine people: direction, not proof. The rehearsal plays a different scenario (S4) so the team can’t remember the answers.

How confident are we?

What this rests on

The scenarios, deadlines, roles, statements and rules are as agreed with the owner and the crisis team on 16 Oct 2026. The legal deadlines are the rules on Inputs, checked on official sources on 16 October 2026; they are not legal advice, and each policy's or contract's own deadline is as the owner read it. Gross profit a working day is counted from the accounts and customers' gross profit from the sales ledger; direct costs and insurance are counted, estimated or quoted as each row says. Days disrupted, customers lost, how far the plan reduces them, and how much less the insurer would pay without the plan are the owner's estimates and assumptions, not tested; customers lost count for the rest of the year after the days disrupted, less the insured share inside the business interruption indemnity period; so is each event's likelihood a year, which is never a fact, so the expected costs hold only with those likelihoods. The readiness measures rest on one baseline exercise and a quiz of 9 people: they show direction, not proof.

The plan is finished when it is handed over and printed; the rehearsal is the first test of it. Check the numbers every six months, and rehearse once a year.