Architecture and interior design for schools, healthcare and commercial clients across Worcestershire and the West Midlands. 32 staff. 34 suppliers from a year of the purchase ledger, excluding VAT.
The plan takes about 65 hours of staff time, worth £2,470.
Business rates and professional registration fees are counted but marked not negotiable.
| Supplier | Category | A year |
|---|---|---|
| Severn Property Holdings | Premises and facilities | £96,000 |
| Draftholm Software | Software and subscriptions | £38,600 |
| Marches Insurance Brokers | Insurance | £28,100 |
| Business rates (local council) | Not negotiable (tax, rates, statutory) | £22,400 |
| Teme IT Support | Telecoms and IT | £21,600 |
| Hensmoor Energy | Premises and facilities | £18,400 |
| Clearview Cleaning Services | Premises and facilities | £14,300 |
| Hartley Accountants | Professional fees | £12,600 |
| Brightline Telecom | Telecoms and IT | £11,200 |
| Cloudsuite Business | Software and subscriptions | £9,850 |
| # | Supplier | Action | Spend a year | Saving a year | Based on | Renewal | Owner | By when |
|---|---|---|---|---|---|---|---|---|
| 1 | Draftholm Software Software and subscriptions | Reduce | £38,600 | £8,770 | Override: 5 unused licences at the current price per licence, from the October 2026 invoice. | Later | Design director | January 2027 |
| 2 | Taskwell Software and subscriptions | Cancel | £4,320 | £4,320 | Full spend | No contract | Practice manager | January 2027 |
| 3 | FileHarbour Software and subscriptions | Cancel | £3,600 | £3,600 | Full spend | No contract | Practice manager | February 2027 |
| 4 | Marches Insurance Brokers Insurance | Retender | £28,100 | £1,405–£4,215 | Assumed starting share | Later | Finance partner | March 2027 |
| 5 | Kestrel Mobile Telecoms and IT | Reduce | £8,640 | £2,160 | Override: 6 unused lines at £30 a month each, from the September bill. | Act within 90 days | Practice manager | November 2026 |
| 6 | Teme IT Support Telecoms and IT | Retender | £21,600 | £1,080–£3,240 | Assumed starting share | Act within 90 days | Finance partner | December 2026 |
| 7 | Hensmoor Energy Premises and facilities | Retender | £18,400 | £920–£2,760 | Assumed starting share | Act within 90 days | Practice manager | December 2026 |
| 8 | Lumen3D Software and subscriptions | Reduce | £6,200 | £930–£2,480 | Assumed starting share | Later | Design director | April 2027 |
| 9 | MeetSpace Software and subscriptions | Cancel | £1,440 | £1,440 | Full spend | No contract | Practice manager | November 2026 |
| 10 | Malvern Water Coolers Premises and facilities | Cancel | £1,150 | £1,150 | Full spend | Act within 90 days | Practice manager | December 2026 |
| 11 | SignRight Software and subscriptions | Cancel | £1,080 | £1,080 | Full spend | No contract | Practice manager | November 2026 |
| 12 | Clearview Cleaning Services Premises and facilities | Renegotiate | £14,300 | £429–£1,430 | Assumed starting share | Later | Practice manager | March 2027 |
| 13 | Brightline Telecom Telecoms and IT | Renegotiate | £11,200 | £336–£1,120 | Assumed starting share | Later | Practice manager | August 2027 |
| 14 | Archive Safe Storage Premises and facilities | Reduce | £2,640 | £396–£1,056 | Assumed starting share | Deadline passed | Practice manager | January 2027 |
| 15 | Printwise Leasing Print and stationery | Renegotiate | £9,400 | £282–£940 | Assumed starting share | Later | Practice manager | May 2027 |
Only actions worth at least £500 a year are listed. "Assumed starting share" means a cautious starting assumption for that kind of action, not a quotation; replace it when a real price comes in.
| Supplier | Spend a year | Last day for notice | Days left | Status | Action |
|---|---|---|---|---|---|
| Archive Safe Storage | £2,640 | 2 Oct 2026 | -10 | Deadline passed | Reduce |
| PeopleSafe HR | £3,480 | 2 Nov 2026 | 21 | Act within 30 days | Renegotiate |
| Kestrel Mobile | £8,640 | 15 Nov 2026 | 34 | Act within 90 days | Reduce |
| Malvern Water Coolers | £1,150 | 31 Dec 2026 | 80 | Act within 90 days | Cancel |
| Teme IT Support | £21,600 | 31 Dec 2026 | 80 | Act within 90 days | Retender |
| Hensmoor Energy | £18,400 | 1 Jan 2027 | 81 | Act within 90 days | Retender |
The archive storage deadline passed before the review, so the contract renews unless the supplier agrees otherwise. The practice will ask to reduce the boxes now, and diary the next deadline. Check each contract's terms, or take advice, before giving notice.
Spend comes from 12 months of the purchase ledger, which is 94% of the costs in the accounts for the same months. Of the mid-case saving, £11,590 is the full spend of suppliers to cancel, £10,930 rests on counted overrides with their own reasons, and £11,510 rests on assumed starting shares for reducing, renegotiating, retendering and consolidating. Savings take effect only once each change is made; contract notice periods may delay them.
The cancellations and the two counted overrides (unused software licences and unused mobile lines) are the firmest figures. The retender and renegotiation figures are the softest: they become real only when quotations come in.
At handover the practice wrote an owner and a date beside each top action and put the notice deadlines in the diary. The agent was then set up in the practice's own AI assistant account, with read-only access to the accounting system. On the second Monday of each month it loads the latest 12 months of the purchase ledger into a new dated copy of the review, runs the checks and sends the finance partner a short note. It uses the rules on Inputs: the £500 smallest saving worth acting on, and a 10% rise in a supplier's spend a year. Nothing left the practice, and no decision changed, without one of its own people approving it. These events continue the fictional example.
| Date | What the agent found | Flag? | What people decided |
|---|---|---|---|
| 9 Nov | Two notice deadlines came within 90 days: Draftholm Software and Pixel & Pine Web, both on 29 January. At the review they were 109 days away. | Flag | The design director confirmed the cut from 22 to 17 Draftholm licences in writing in December. The marketing lead asked Pixel & Pine for a lighter care plan. |
| 9 Nov | A new supplier appeared in the purchase ledger: Vantra Render, a cloud rendering service first invoiced in September, £820 so far, above the £500 smallest saving. The agent added it with use Don't know until someone decided. | Flag | The design director had taken it out for two hospital projects. It overlaps with the six Lumen3D licences, so both will be decided together before Lumen3D's 1 May deadline. |
| 14 Dec | SignRight, due to be cancelled by November, sent another invoice on 1 December (£90). | Flag | The practice manager found the cancellation had gone to an old account email, sent it again from the admin account and asked for the December charge back. |
| 14 Dec | Printwise Click Charges rose to £5,712 a year, 12% above the review, more than the 10% rise set on Inputs. | Flag | Expected: the A1 drawing sets for the hospital tender. No change now; the per-page rate stays in May's renegotiation. |
| 11 Jan | Hensmoor Energy appeared twice after the bookkeeper opened a second supplier account for its new contract. Checks showed CHECK, so the note reported a data problem and no figures. | Flag | The practice manager combined the two rows and asked for the old account code to be closed. |
| 12 Jan | Rerun after the fix: all checks passed and nothing new crossed a line. The note listed Draftholm and Pixel & Pine at 17 days from their deadlines, both in hand. | Note only | Nothing needed. The finance partner read the note. |
At the check-in on 3 December, about day 45 and after the first monthly run, Geoff and the finance partner read the first run's log together. No rule needed changing, and Geoff's upkeep of the set-up ended there.
What the agent added. The method is unchanged: same spreadsheet, same checks, same decisions. The agent made sure the ledger was looked at every month, not once a year. It caught a new subscription that duplicated one already paid for within two months of its first invoice, and a cancellation that had not happened, a month after it was due. The benefit here is that the review's savings held and new spend was seen early; no new £ figure is claimed for it.
Fictional and labelled: these events continue the worked example. The same six events are the sample rows in the Agent log of the worked-example spreadsheet. The agent is part of the guided and done-for-you routes; the self-implement kit does not include it.