Value Stream Map · October 2026

Wenlow Cabinets Ltd

Kitchen and bedroom cabinets made to order for independent kitchen retailers and housebuilders. 52 staff. All cabinets, standard and made to measure, counted per cabinet (the same machines make every cabinet).

Worked example. Wenlow Cabinets and its figures are fictional. All figures come from the worked-example spreadsheet: ALL CHECKS PASSED (with 2 notes).
The headline

A cabinet takes 27 working days to get 38 minutes of work: the future state cuts that to 10 days and frees £72,380

Lead time
27.5 → 9.7 d
working days from order to despatch, now and in the future state
Cash released
£72,380
one-off, from £109,520 to £37,140; £11,000 of it finished goods
A year
£38,502
overtime £18,000, rejects £13,264, holding cost £7,238; changes cost £14,500
Bottleneck
132%
edge banding loaded today (68 a day against 90); 83% in the future state

Verdict: Today a unit takes 27.5 working days from order to despatch, of which 38 minutes of work add value (0.33%). Edge banding can't keep up with demand (68 a day against 90), so overtime covers the gap. The future state cuts the lead time to 9.7 days with every step under 85% loaded, releases £72,380 of cash and saves £38,502 a year for £14,500 of one-off changes (payback 5 months).

Current state

Where the time goes today

I3604.0 dDrawings andcutting listC/T 2.0 minC/O 0 min/dayUptime 95%FTR 97%194/day · 47% ✓I6006.7 dBeam sawC/T 3.5 minC/O 60 min/dayUptime 90%FTR 98%91/day · 99% ✓I4204.7 dEdge bandingC/T 4.0 minC/O 60 min/dayUptime 80%FTR 95%68/day · 132% ✗I3003.3 dCNC drillingC/T 3.5 minC/O 30 min/dayUptime 85%FTR 97%92/day · 98% ✓I3804.2 dAssemblyC/T 3.2 minC/O 0 min/dayUptime 95%FTR 96%120/day · 75% ✓I1501.7 dQuality checkand wrapC/T 2.5 minC/O 0 min/dayUptime 95%FTR 99%158/day · 57% ✓I2602.9 dFinished4.0 d2.0 min6.7 d3.5 min4.7 d4.0 min3.3 d3.5 min4.2 d3.2 min1.7 d2.5 min2.9 dCURRENT STATE · demand 90 a day · takt 4.67 min · lead time 27.5 working days · value-adding work 38 min

Triangles are what waits before each step, in cabinets and working days at today's demand. Boxes show cycle time (C/T), changeover minutes a day (C/O), uptime, first time right (FTR), good units a day and loading (demand ÷ capacity); a red box can't keep up with demand, and three steps run above 85% loaded, so queues build in front of them. The ladder underneath adds up the waiting days and the working minutes: the minutes in red are the steps that add value the customer pays for (their work content: cycle time × people working in parallel adds up to 38 minutes). Edge banding makes 68 good cabinets a day against demand of 90: changeovers, jams and rework, covered today by overtime.

Future state

The plan

I1802.0 dDrawings andcutting listC/T 2.0 minC/O 0 min/dayUptime 95%FTR 99%198/day · 46% ✓I2703.0 dBeam sawC/T 3.2 minC/O 30 min/dayUptime 92%FTR 98%110/day · 82% ✓I901.0 dEdge bandingC/T 3.4 minC/O 15 min/dayUptime 93%FTR 98%109/day · 83% ✓I600.7 dCNC drillingC/T 3.3 minC/O 20 min/dayUptime 92%FTR 99%110/day · 82% ✓I901.0 dAssemblyC/T 3.2 minC/O 0 min/dayUptime 95%FTR 98%122/day · 74% ✓I450.5 dQuality checkand wrapC/T 2.5 minC/O 0 min/dayUptime 95%FTR 99%158/day · 57% ✓I1351.5 dFinished2.0 d2.0 min3.0 d3.2 min1.0 d3.4 min0.7 d3.3 min1.0 d3.2 min0.5 d2.5 min1.5 dFUTURE STATE · demand 90 a day · takt 4.67 min · lead time 9.7 working days · value-adding work 36 min

Three steps change. Edge banding gets quick-change glue pots, colour sequencing (three changeovers of 5 minutes instead of four of 15), a jam-clearing routine (uptime 80% to 93%) and a feed-speed change (4.0 to 3.4 minutes). The beam saw gets nesting software and colour sequencing; CNC drilling a fixture change and planned maintenance. Every step then runs at or under 85% loaded, so the overtime stops and capped buffers can hold: a cabinet waits about a day rather than four or five before each step. Drawing checks, CNC programme checks and assembly jigs cut rejects. About £61,380 of the cash comes back from boards and work in progress as purchasing falls over the following weeks; the £11,000 from finished goods depends on housebuilders' delivery slots.

NowFutureChange
Lead time (working days)27.59.7−17.8
Share of lead time adding value0.33%0.88%
Cash in stock and work in progress£109,520£37,140−£72,380
Cost of rejects a year£24,627£11,363−£13,264
Bottleneck loading132%83%
One-off cost of the changes; payback£14,5005 months
How confident are we?

What this rests on

One product family, counted in one unit, from a walk on one day: stock and work in progress were counted once, so the lead time is a snapshot (Little's law: units waiting ÷ demand a day). Capacity uses the normal 420 minutes a day without overtime, times each step's share for this family, less changeovers, times uptime and first time right; the future state must keep every step under 85% loaded. Cash is materials and bought-in parts only; cash released from raw materials comes back as lower purchasing over a few weeks, and finished goods only fall if delivery timing allows. The future state is the team's plan, not a forecast. A shorter lead time is often worth more than the cash (more orders won, fewer expedites) but is not valued here.