| 29 Sep 2026 | Walk invitations drafted for the four processes: the roles who do the work, about an hour each, and what it is for (the process, not anyone's performance; times recorded by role) Processes sheet; the process walk guide | Draft | Managing director Approved | Sent by the managing director on 30 Sep. Walks held 5 to 9 Oct. |
| 1 Oct 2026 | Runs a month collated from system records: 1,260 supplier invoices posted July to September (420 a month) and 480 artwork jobs (160 a month) Xero and the job system, read-only | Logged | Finance manager Approved | Confirmed by the finance manager and the customer service adviser; entered on Processes. |
| 5 Oct 2026 | Two walks to be recorded (supplier invoices; artwork to proof) with every participant's written consent, signed before the walk Consent forms in the walks folder; Inputs (recorded: Yes) | Logged | The consultant Decided | The timesheet and new-starter walks weren't recorded: one participant preferred not, so the consultant took notes by hand. |
| 9 Oct 2026 | 27 step rows drafted from the transcripts and notes: step, role, system, the doer's own minutes and where each came from, and a proposed step type. No treatments or changes proposed Transcripts (P1, P4) and the consultant's notes (P2, P3) | Coded | The consultant Approved with changes | The consultant changed one type (matching invoices to orders: Checking, not Necessary). Treatments and changes were left for the working session. |
| 9 Oct 2026 | Two steps with no time given in the walk: collecting timesheets (P2) and finding the induction documents (P3) Walk notes; Steps (minutes blank) | Flag | The consultant Decided | The doers gave their own estimates on 12 Oct, recorded as Estimated by the doer. |
| 13 Oct 2026 | Timesheet steps hold personal data where a mistake costs a lot: digital clocking-in (C4) is Controls first Steps (data and consequence columns); Changes | Flag | Managing director Decided | C4 waits for data protection advice and a risk assessment. The walk notes for it describe the data by type and role only. |
| 19 Oct 2026 | Reminders drafted for the two changes due in November: approval limits (C3) and the artwork checklist (C8) Changes (owner, by when); Inputs (14 days before) | Draft | Managing director Approved | Sent on 19 Oct. C3 live on 13 Nov. |
| 2 Dec 2026 | The artwork checklist (C8, November) not reported done Changes; the owner's update | Flag | Managing director Decided | The customer service adviser added it to the order confirmation on 7 Dec. |
| 18 Dec 2026 | Reminder drafted for the invoice workflow (C1, January) Changes (owner, by when) | Draft | Managing director Approved | Sent to the finance manager. Live on 26 Jan. |
| 11 Jan 2027 | Re-timing prepared: approving non-stock invoices (P1 step 7) from 15 Feb 2027, three months after C3; re-proofs (P4 step 5) from 8 Mar 2027, three months after C8. Timed by the people who do them, by role Steps (by change); Inputs (3 months) | Draft | Managing director Approved | In the process owners' diaries. The treatment shares stay as they are until the new times are in. |